Skip to main content
Clean Hydrogen Partnership

Release from the storage of a hydrogen production plant

Event

Event ID
1086
Quality
Description
The accidental hydrogen release occurred when testing the storage system connected to a PEM electrolyser.
The leak test consisted in filling the storage with hydrogen at step-wise increase of pressure. After the step at 3 bar (0.3 MPa), which did not reveal any leak, the storage was pressurised up to 5 bar (0.5 MPa). At that moment a hissing sound occurred from the storage at the outside of the building indicating a leak. The production of hydrogen was stopped and all shut-off valves were closed automatically.

Since the leak took place on the 'storage side of the shut-off valves, the leaking continued. The operator decided then to let the storage bleed out. Afterwards, the location of the leak was found and isolated by closing of nearby manual valves.
The leak was located on a flanged connection near the storage. Bolts on this flange were found loose after the incident.
The exact cause of the leak could not be identified.
A possible explanation was that the torqued connection might have become loose when installing the vent line due to the manoeuvring of the pipe. The vibration of the leak could have further loosen the bolts.
The gasket was replaced, the bolts were retightened and torqued and the storage was leak tested up to 33 bar (3.3 MPa) without any other leaks.

Approximately 224Nm³ were released in 60 minutes.
Event Initiating system
Classification of the physical effects
Unignited Hydrogen Release
Nature of the consequences
Leak No Ignition (No additional details provided)
Macro-region
Europe
Country
Norway
Date
Main component involved?
Flange (Bolts)
How was it involved?
Leak
Initiating cause
Loss Of Tightness (Wrong Operation)
Root causes
Root CAUSE analysis
The leak was most likely caused by the manoeuvring of the piping during the installation of the vent line. The case showed that the storage system did not have a depressurisation system by its own.

Facility

Application
Hydrogen Production
Sub-application
water electrolysis
Hydrogen supply chain stage
All components affected
Flange, vent, CGH2 storage vessel
Location type
Open
Operational condition
Pre-event occurrences
The event took place during the commissioning stage of the hydrogen installation. The storage was being
filled with hydrogen up to a pressure of 5 bar.

Description of the facility/unit/process/substances
DESCRIPTION of the FACILITY
2.5 MW (1.25 MW stacks x2) electrolyser connected to a wind farm

Emergency & Consequences

Number of injured persons
0
Number of fatalities
0
Post-event summary
No damage or injuries were reported due to this incident

Lesson Learnt

Lesson Learnt

The safety system in place worked as planned. However, since the leak was located on the 'storage side' of the shut-off valves, the leaking continued till emptying of the storage system.
After that, as immediate corrective measure, the gasket was replaced, the bolts were retightened and torqued and the storage testing restarted.
As long term measure correcting the initial design, it was decided to add an automated depressurisation system to the storage, to release pressure in case of a malfunctioning or failure.

Event Nature

Release type
gas
Involved substances (% vol)
H2 100%
Release duration
1 h
Release rate
20kg/h
Released amount
224Nm³
(ca. 20 kg)
Actual pressure (MPa)
0.3
Design pressure (MPa)
3.3
Presumed ignition source
No ignition

References

Reference & weblink

Own report available but confidential

JRC assessment