Event
- Event ID
- 1086
- Quality
- Description
- The accidental hydrogen release occurred when testing the storage system connected to a PEM electrolyser.
The leak test consisted in filling the storage with hydrogen at step-wise increase of pressure. After the step at 3 bar (0.3 MPa), which did not reveal any leak, the storage was pressurised up to 5 bar (0.5 MPa). At that moment a hissing sound occurred from the storage at the outside of the building indicating a leak. The production of hydrogen was stopped and all shut-off valves were closed automatically.
Since the leak took place on the 'storage side of the shut-off valves, the leaking continued. The operator decided then to let the storage bleed out. Afterwards, the location of the leak was found and isolated by closing of nearby manual valves.
The leak was located on a flanged connection near the storage. Bolts on this flange were found loose after the incident.
The exact cause of the leak could not be identified.
A possible explanation was that the torqued connection might have become loose when installing the vent line due to the manoeuvring of the pipe. The vibration of the leak could have further loosen the bolts.
The gasket was replaced, the bolts were retightened and torqued and the storage was leak tested up to 33 bar (3.3 MPa) without any other leaks.
Approximately 224Nm³ were released in 60 minutes. - Event Initiating system
- Classification of the physical effects
- Unignited Hydrogen Release
- Nature of the consequences
- Leak No Ignition (No additional details provided)
- Macro-region
- Europe
- Country
- Norway
- Date
- Main component involved?
- Flange (Bolts)
- How was it involved?
- Leak
- Initiating cause
- Loss Of Tightness (Wrong Operation)
- Root causes
- Root CAUSE analysis
- The leak was most likely caused by the manoeuvring of the piping during the installation of the vent line. The case showed that the storage system did not have a depressurisation system by its own.
Facility
- Application
- Hydrogen Production
- Sub-application
- water electrolysis
- Hydrogen supply chain stage
- All components affected
- Flange, vent, CGH2 storage vessel
- Location type
- Open
- Operational condition
- Pre-event occurrences
- The event took place during the commissioning stage of the hydrogen installation. The storage was being
filled with hydrogen up to a pressure of 5 bar. - Description of the facility/unit/process/substances
- DESCRIPTION of the FACILITY
2.5 MW (1.25 MW stacks x2) electrolyser connected to a wind farm
Emergency & Consequences
- Number of injured persons
- 0
- Number of fatalities
- 0
- Post-event summary
- No damage or injuries were reported due to this incident
Lesson Learnt
- Lesson Learnt
The safety system in place worked as planned. However, since the leak was located on the 'storage side' of the shut-off valves, the leaking continued till emptying of the storage system.
After that, as immediate corrective measure, the gasket was replaced, the bolts were retightened and torqued and the storage testing restarted.
As long term measure correcting the initial design, it was decided to add an automated depressurisation system to the storage, to release pressure in case of a malfunctioning or failure.
Event Nature
- Release type
- gas
- Involved substances (% vol)
- H2 100%
- Release duration
- 1 h
- Release rate
- 20kg/h
- Released amount
- 224Nm³
(ca. 20 kg) - Actual pressure (MPa)
- 0.3
- Design pressure (MPa)
- 3.3
- Presumed ignition source
- No ignition
References
- Reference & weblink
Own report available but confidential
JRC assessment
- Sources categories
- Investigation report