Skip to main content
Clean Hydrogen Partnership

Release from a hydrogen refuelling station

Event

Event ID
913
Quality
Description
The release occurred in the hydrogen storage system of a refuelling station.
In the night a leakage occurred at one of the 120 high pressure bottles (800 bar). The leakage occurred at a screwed fitting at the bottle-to-pipe connection. Three of the three sensors installed at nearby control panels detected the hydrogen (signal threshold 0. 40 % LEL) and lead to an immediate shutdown of the station.
The affected high pressure bank was separated from the other banks so that a maximum of only 60 kg could be released, corresponding to the total inventory of one bank. No ignition took place.
A pedestrian heard the alarm and called the police, who called the station manufacturer. In parallel, the operation team received the alarm at their remote monitor. Police called the fire brigade and installed a safer perimeters of 200 m, closing all the roads.
The station manufacturer technicians were called on-site and arrived 2 hours later. They started a controlled additional de-pressurisation through a vent line bypass which brought the hydrogen to the bus dispenser vent line. After approximately 5 hours, the pressure in the affected hydrogen container was at around 1-2 bar and could be sealed again.
Event Initiating system
Classification of the physical effects
No Hydrogen Release
Nature of the consequences
Macro-region
Europe
Country
Germany
Date
Root causes
Root CAUSE analysis
The INITIATING CAUSE was a leakage from a connection.
It particular, was known that the screwed connection at the high-pressure bottle could fall fail with a higher probability during start-up of operation and during the first 200 cycles . System design of the screwed fitting was not allowing more than 7 kg/h of flow from such a leakage.
The safety measures in place worked as designed and the emergency was managed successfully, avoiding escalation.
The incident highlighted nevertheless some shortcoming in mitigating measures for worse-case scenario (possible ignition of the hdyrogen) and in emergency communication (the leak was discovered by a person passing-by, there was no ad-hoc alarm aiming at warning operators).

Therefore, the ROOT CAUSE could be idenfied inshortcomings of the (safety system) design.

Facility

Application
Hydrogen Transport And Distribution
Sub-application
HRS
Hydrogen supply chain stage
Hydrogen Storage (No additional details provided)
All components affected
storage bottle
Location type
Confined
Operational condition
Description of the facility/unit/process/substances
DESCRIPTION OF THE FACILITY
The storage system of the HRS consisted in 4 high pressure banks. Each bank consisted of 30 bottles at 800 bar, with a total of 60 kg/bank and a total ivnentory of 240 kg.

Emergency & Consequences

Number of injured persons
0
Number of fatalities
0
Environmental damage
0
Post-event summary
No damage.
Official legal action
An official systematic investigation into the failure cause was expected to be started, subject to appointment of a consultant by the civil court .

Lesson Learnt

Lesson Learnt

The automatic alarm systems and safeguards worked as planned, and effectively minimised the amount of hydrogen released.
However, the consequences would have been different in case of (delayed) ignition in a confined space.
On top of the lessons learnt which brought to the corrective measures adopted, a general lesson learnt regarded the need to organise training for worst-case scenarios, including drill exercises .


Corrective Measures
S
(1) A long plan firewall has been installed 2 days after the incident, to protect other cylinders from jet flame coming for one of them. This had already been planned before the accidental release.
(2) As a further cylinders protection against overheating, a dry sprinkler system was installed above the high-pressure storage banks.
(3) The alarm system was modified. The audible alarms will continue only for 1 minute (sirens in outside areas were audible from far away) while the visible alarms will continue. An additional alarm notification via SMS and on audible basis was installed at operators control room, to allow an immediate notification to the operator.
(4) The storage pressure was reduced in 3 of 4 banks to 600 bar until additional measures have been implemented.
(5) Emergency plans and procedures were reviewed, improved and documented.

Event Nature

Release type
gas
Involved substances (% vol)
H2 100%
Release duration
5 h
Release rate
5 kg/h
Released amount
26 kg
Actual pressure (MPa)
80
Design pressure (MPa)
80
Presumed ignition source
No release

References

Reference & weblink

Investigation report of the related project (not publicly available)

The event is reported and analysed, with interesting assumptions and discussion, by:<br />
Ayi et al, Is hydrogen ignition data from literature practically observed?, 89 (2024) 746-759<br />
https://doi.org/10.1016/j.ijhydene.2024.09.269 <br />
(accessed January 2025)

Also in H2TOOLS <br />
https://h2tools.org/lessons/hydrogen-cylinder-leak-fueling-station<br />
(accessed Sept 2025)

JRC assessment